THE CHALLENGE
The starting point.
Vibration and wear at the short rail transitions were affecting trolley travel. Following an earlier A75 rail project, STARKON was selected to carry out work on two further cranes using A100 short rails.
CRANE PARTS & SERVICE / GMP LE HAVRE
Design, production and replacement of A100 short rail components, combined with repair of the supporting rail bed.

THE CHALLENGE
Vibration and wear at the short rail transitions were affecting trolley travel. Following an earlier A75 rail project, STARKON was selected to carry out work on two further cranes using A100 short rails.
OUR SCOPE
The team designed and produced eight short rail pieces for the two cranes. Component preparation was coordinated with the site programme, where the rails were replaced and the rail bed repaired.
THE RESULT
The completed work restored a smoother trolley transition. Component manufacture and repair of the support beneath the rail were treated as part of the same job.