THE CHALLENGE
The starting point.
The vessel’s limited time in port provided a short opportunity to inspect and realign its reel-drive installation. STARKON had previously been involved in construction of the NOV equipment.
MECHANICAL SERVICE / SEVAN VEGA
Preventive inspection and alignment of the reel-drive shafts and couplings aboard Sevan Vega.

THE CHALLENGE
The vessel’s limited time in port provided a short opportunity to inspect and realign its reel-drive installation. STARKON had previously been involved in construction of the NOV equipment.
OUR SCOPE
Working with NOV and the vessel’s crew, the team inspected the drive and adjusted the shafts and couplings. Additional shims were machined on board to complete the alignment work.
THE RESULT
The project was completed over five working days, returning the drive to smooth operation before the vessel continued its programme.